Washington Avenue Construction Update
Posted August 23, 2024The NJ D.O.T. is wrapping up the the second section of the first stage of the Washington Avenue construction project. Today, they began to remove the concrete barriers on Washington Avenue. The roadway should be completely reopen on Monday, August 26, 2024. They will start construction again on or about September 3, 2024 (weather permitting) on Washington Avenue from Rossmore Place to Division Avenue. Each section should take approximately 15 days to complete. The area in front of our middle school will be clear of any construction by the time school starts. Please continue to monitor this site as well as the Police Department's social media page for updates on this project. As always, thank you for your patience during this time.